Ocean Terminal rebuild passes 60%

Georgia Ports Authority says its Ocean Terminal renovation has moved from 55 percent complete in June to more than 60 percent complete, with the full 2,650-foot berth finished and working ships and the truck gate now operational.

Gallery1 / 2

lead image (publisher's social card)
Project imagelead image (publisher's social card)Steven Alford / Georgia Ports Authority — Savannah's Ocean Terminal renovations 60 percent complete
AI editorial concept showing a container ship at a crane-lined berth above torn-paper panels of a truck gate and a container yard.
Project contextAI editorial concept showing a container ship at a crane-lined berth above torn-paper panels of a truck gate and a container yard.Urban Savannah / AI-assisted editorial concept

Georgia Ports Authority says the $1.6 billion Ocean Terminal rebuild is now more than 60 percent complete. The full 2,650-foot berth is serving ships, and the new truck gate has 12 inbound and six outbound lanes. The 200-acre terminal is being expanded from 200,000 to 1.75 million annual container units, with the first yard phase due in fall 2027 and full completion expected by the end of 2028.

Why it matters

The project is converting a 200-acre terminal into much larger container capacity, taking annual capacity from 200,000 TEUs to 1.75 million TEUs while adding direct interstate truck access.

JurisdictionCity of Savannah
Scale$1.6B · 200 acres · 1.75M TEUs
TimelineFirst yard phase fall 2027 · full yard end of 2028
WhoGeorgia Ports Authority
Sources and documents4 sources

See an error, or have an update on this project? Tell Urban Savannah.