Effingham signed OpenAI's tax break under an NDA, five months before the public knew

Records show Effingham's economic development officials negotiated OpenAI's $20 billion data center tax break under a non-disclosure agreement starting in February, and the public wasn't told until the day after the county signed.

Gallery1 / 2

Savannah Gateway Industrial Hub sign, the site of the planned data center campus
Project imageSavannah Gateway Industrial Hub sign, the site of the planned data center campusEffingham County Development Authority
Aerial view across Effingham County forest toward nearby industry.
Project contextAerial view across Effingham County forest toward nearby industry.Project Camellia (OpenAI)

Effingham County's industrial development authority signed a mutual non-disclosure agreement with OpenAI on February 2, then spent five months negotiating in private before the county signed a memorandum of understanding with Octans GA LLC, an OpenAI affiliate, on July 21.

The public announcement came the next day. Records obtained by WTOC show the deal was worked out by IDA CEO Brandt Herndon, Vice President Jessica Hood, County Manager Tim Callanan and School Superintendent Yancy Ford.

The tax terms are unusual even by data-center standards. Georgia normally assesses property at 40% of fair market value; this deal locks OpenAI's assessment at 25% for 15 years per project phase, a 37.5% annual cut, with the tax rate frozen at 2026's millage.

After 15 years, OpenAI can buy the property back from the county for $10. The project itself, five phases on 1,400 acres at the Savannah Gateway Industrial Hub outside Rincon, is unchanged from what cleared last week: four buildings, 3.2 gigawatts of Georgia Power capacity delivered 2028 to 2032, construction starting late 2028 and running through 2034.

Residents who found out after the fact are the story now. "If it's such a great thing for this area, why isn't it being done out in the open?" resident Wade Britt told WTOC. County Manager Callanan defended the secrecy as standard for a deal of this size, pointing to the jobs and to a promised cut in homestead property taxes of up to 40%.

Why it matters

The tax mechanics mean OpenAI pays 37.5% less than a normal Effingham property owner for 15 years, then can buy the land back for the price of a cup of coffee, and county officials agreed to all of it before residents were allowed to know it was happening.

What to watch

The building moratorium clock keeps running toward 2028 groundbreaking; whether Effingham publishes future incentive deals before signing, not after, is the open question this story leaves behind.

JurisdictionEffingham County
Scale$20B investment, 1,400 acres, four buildings, 3.2 GW
TimelineNDA signed Feb. 2; MOU signed July 21; construction 2028–2034
WhoEffingham County Industrial Development Authority / OpenAI
Sources and documents5 sources

See an error, or have an update on this project? Tell Urban Savannah.

Connected coverage

Follow the thread

All updates →

Explore the projects, places, developers and public systems connected to this story. Each card explains the link.

Aerial view across Effingham County forest toward nearby industry.GA

Same projectProject Camellia (OpenAI Effingham data center)

Both involveOpenAI + Project Camellia

Milestone

State completes its regional-impact review of OpenAI's $20B Effingham County data center

Georgia's Development of Regional Impact review of Project Camellia, OpenAI's proposed data-center campus in Effingham County, is now complete on the state's own tracking system: the Coastal Georgia Regional Development Commission issued its finding Sept. 1, 2026, with the process marked complete as of Sept. 6.

GA Sep 6, 2026
Project: Project Camellia (OpenAI Effingham data center)
Savannah Mayor Van Johsnon sits among city council which unanimously voted for a data center moratorium on Aug. 27
The Effingham County Industrial Development Authority had a special called meeting, Monday, to vote on three separate agenda items related to Project Camellia and Effingham County's Project Zero. From
~30-45 min from Savannah

Same projectProject Camellia (OpenAI Effingham data center)

Both involveEffingham County Industrial Development Authority + OpenAI +1 more

Zoning

Savannah puts a 155-day hold on large data centers as Effingham's $20B OpenAI campus clears its power deal

City Council froze new large-load data centers for 155 days to rewrite zoning rules, the same week Georgia regulators cleared the power contract for OpenAI's $20 billion Project Camellia campus in neighboring Effingham County.

~30-45 min from Savannah Aug 31, 2026
Project: Project Camellia (OpenAI Effingham data center)
Aerial view across Effingham County forest toward nearby industry.
Savannah Gateway Industrial Hub sign, the site of the planned data center campus
Effingham County

Same projectProject Camellia (OpenAI Effingham data center)

Both involveProject Camellia

Milestone

Effingham pauses OpenAI's data center and starts writing rules to limit it

Effingham County pulled the Project Camellia site plan from its September agenda and told staff to draft binding limits, days before a state report put the data center's power demand at 3,210 megawatts, more than both new reactors at Plant Vogtle combined.

Effingham County Sep 14, 2026
Project: Project Camellia (OpenAI Effingham data center)