The U.S. Army Corps of Engineers extended public comment on Octans GA’s Project Camellia wetlands permit application from November 4 to December 3. The pending application seeks authorization for 72.17 acres of wetland impact, including 50.10 newly proposed acres and 22.07 acres previously authorized for the industrial park.
Why it matters
The federal review covers wetland work needed for the proposed 1,336.14-acre data-center campus near Rincon. The extension gives the public another month to comment, but it is not a permit approval and does not authorize construction in the affected wetlands.
What to watch
Public comments on permit application SAS-2026-00872 are due December 3; the Corps must still complete its Clean Water Act review and decide whether to issue the permit.