The U.S. Army Corps of Engineers extended public comment on Octans GA’s Project Camellia wetlands permit application from November 4 to December 3.

Gallery1 / 3

Official preferred Project Camellia site plan showing four data-center pads, wetland areas and proposed wetland impacts.
Site planThe Corps permit application’s preferred site plan maps the proposed Project Camellia campus and its wetland impacts; the application remains pending.U.S. Army Corps of Engineers / Octans GA / Sligh Environmental Consultants
Aerial view across Effingham County forest toward nearby industry.
Project contextAerial view across Effingham County forest toward nearby industry.Project Camellia (OpenAI)
The Effingham County Industrial Development Authority held a special called meeting to vote on three agenda items related to Project Camellia and Project Zero. From left: ECIDA CEO Brandt Herndon; board members Eric Johnson, Trisha Boyett, Justin Cribs and Jake Patrick; secretary Lon Harden; board chair Matt Saxon; board vice chair Slade Helmly; and attorney Chris Murphy.
Project contextThe Effingham County Industrial Development Authority held a special called meeting to vote on three agenda items related to Project Camellia and Project Zero. From left: ECIDA CEO Brandt Herndon; board members Eric Johnson, Trisha Boyett, Justin Cribs and Jake Patrick; secretary Lon Harden; board chair Matt Saxon; board vice chair Slade Helmly; and attorney Chris Murphy.Lucille Lannigan / Effingham Herald

The U.S. Army Corps of Engineers extended public comment on Octans GA’s Project Camellia wetlands permit application from November 4 to December 3. The pending application seeks authorization for 72.17 acres of wetland impact, including 50.10 newly proposed acres and 22.07 acres previously authorized for the industrial park.

Why it matters

The federal review covers wetland work needed for the proposed 1,336.14-acre data-center campus near Rincon. The extension gives the public another month to comment, but it is not a permit approval and does not authorize construction in the affected wetlands.

What to watch

Public comments on permit application SAS-2026-00872 are due December 3; the Corps must still complete its Clean Water Act review and decide whether to issue the permit.

JurisdictionEffingham County
ScopeRegional
Site1,336.1 acres
StageMajor Filing
Sources and documents2 sources

See an error, or have an update on this project? Tell Urban Savannah.

Connected coverage

Follow the thread

All updates →

Explore the projects, places, developers and public systems connected to this story. Each card explains the link.

Aerial view across Effingham County forest toward nearby industry.Effingham County

Same projectProject Camellia

Same placeEffingham County

Zoning

Project Camellia faces a new damages lawsuit

Three Effingham County residents filed a new damages complaint in State Court on November 6 against OpenAI entities, the county development authority, county officials and a private land agent over how Project Camellia's land, zoning and incentive arrangements were handled.

Effingham County Nov 6, 2026